Project Overview
Two heavy-duty Westinghouse 501aa gas turbines installed and commissioned in Santo Domingo, delivering vital baseload and reserve margins.
Key Specifications
- Turbine Generator Count: 2 Units
- Turbine Technology: Westinghouse 501aa (Westinghouse)
- Project Capacity: Approximately 120 MW
- Site Location: Santo Domingo, Dominican Republic (Caribbean)
- Classification: Turnkey EPC
EPC Delivery Scope
IBC Turbo executed the comprehensive project lifecycle under our signature “IBC Team” methodology. Our scope encompassed:
- Initial site geotechnical and feasibility verification
- Fast-track equipment sourcing, inspection, and logistics handling
- Mechanical installation, electrical interconnects, and balance of plant integration
- Cold and hot commissioning, performance guarantee testing, and commercial handover.