Project Overview
Two GE Alstom Frame 5PA units delivered and commissioned at the Palo Seco site in Puerto Rico to reinforce island grid resilience and rapid response.
Key Specifications
- Turbine Generator Count: 2 Units
- Turbine Technology: GE Alstom Frame 5PA (GE / Alstom)
- Project Capacity: Approximately 50 MW
- Site Location: Palo Seco, Puerto Rico (Caribbean)
- Classification: Turnkey EPC
EPC Delivery Scope
IBC Turbo executed the comprehensive project lifecycle under our signature “IBC Team” methodology. Our scope encompassed:
- Initial site geotechnical and feasibility verification
- Fast-track equipment sourcing, inspection, and logistics handling
- Mechanical installation, electrical interconnects, and balance of plant integration
- Cold and hot commissioning, performance guarantee testing, and commercial handover.